Cleveland Water is replacing approximately 250-feet of water main on Wicklow Road between Shaker Blvd. to 2734 Wicklow Rd. Residents directly impacted have been notified by the contractor (Noce Construction). The work will start Monday, October 27 and last approximately three weeks. No excavation work will start until Monday, November 3. During construction, Wickow will be local access only (i.e. closed to through traffic).
News Flash
Emergency water main replacement: Wicklow Rd.
Construction Updates
Posted on October 27, 2025